1. Environmental Baseline Surveys / Environmental Condition Report |
a. EIS No. 20100381, Draft Supplement, USAF, FL, Eglin Base Realignment and Closure, Proposed Beddown of the Joint Strike Fighter (JSF) and Establishment of an Initial Joint Training Site (IJTS), Implementation, Okaloosa, Walton, and Santa Rosa Counties, FL: b. A revised Environmental Impact Statement is currently in “interim draft” status as of August 2010. c. “Revised Draft Environmental Baseline Survey for the Eglin Air Force Base and Hurlburt Field Military Family Housing Privatization Initiative,” dated August 2010. (Electronic copy available on CD by request) |
2. Building Codes and Standards |
a. Okaloosa County is required by state law to comply with the Florida Building Code of 2007 and all of the latest amendments. (The current code is the Florida Building Code of 2007; the 2010 Code will be the controlling version at the time of project closing.) For further information visit the Florida Building Commission website at http://www/floridabuilding org/c/default.aspx. b. ASCE-7SEI 24-05 (Flood/Water intrusion standards) c. Fortified Builders Guide available at http://www.ibhs.org |
3. Installation Restoration Program (IRP) |
There are no IRP sites in the Leased Premises
|
4. General Plan |
“Hurlburt Field General Plan, 90% Submittal,” prepared by Woolpert, dated August 2010 (this document is available on CD by request).
|
5. Military Family Housing Community Profile (HCP) |
“Hurlburt Field Housing Community Profile Report” prepared by JM Waller Associates / Parsons 3D/I dated 10 October 2008 (this document is available on CD by request).
|
6. Family Housing Master Plan (FHMP) |
“Hurlburt Field Family Housing Master Plan,” dated 25 Aug 2006.
|
7. Housing Requirement and Market Analyses (HRMA) |
HRMA Hurlburt Field, Florida, 2009 – 2014, prepared by SAIC, October 2009. |
8. AICUZ Studies |
Hurlburt Field 2008 AICUZ Noise Contours (DB) Printed 7 Oct 2010 |
9. Integrated Natural Resource Management Plans (INRMP) |
Prepared by Science Applications International Corporation (SAIC), dated May 2008. |
10. Standards and Guidelines for Construction, found in City/County Ordinances |
See Section 2 “Building Codes and Standards” above. |
11. Radon test results |
Performed by 646 MG/SGB, originally tested in August, 1994.
|
12. Asbestos and Lead-Based Paint Identification Surveys |
Performed by Parsons, dated April 1996 (available in base document room only).
|
13. Base-Specific Documents |
a. AFSOCI 33-105 “AFSOC Communications Specifications For Facility Construction and Alterations” b. Family Housing Brochure, dated 1 April 2010 c. Hurlburt Field Floodplain Information: Includes (a) three FEMA Maps (2002),and (b) nine flood elevation certificates Flood Elevation Certificates (available in Document Room) d. Hurlburt Field Housing Maintenance Contract with THOMCO f. Hurlburt Field Street Names, dated 27 September 2010 g. Hurlburt Grounds Maintenance Contract with ALLSERVE j. Refuse contract with Dorado Services Inc. k. “Summary of Coastal Construction Requirements and Recommendations” August 2005 l. Reserved m. Reserved n. Landscape Development Plan [Link Added 5 Nov 2010] o. Topographical Map [Link Updated 15 Nov 2010] p. Hurlburt Field Utility Consumption FY10 [Link Added 29 Nov 2010] |
Occupancy Reports |
a. 2008 b. 2009 c. 2010 [Link Updated 4 Nov 2010] |
Maps / Drawings / Utilities |
a(i). Water Supply System (PNG) a(ii). Water Supply System (PDF) [Link Updated 12 Nov 2010] b(i). Sanitary Sewer System (PNG) b(ii). Sanitary Sewer System (PDF) [Link Updated 12 Nov 2010] c(i). Primary Electrical Distribution System (PNG) c(ii). Primary Electrical Distribution System (PDF) [Link Updated 12 Nov 2010] d(i). Natural Gas Distribution System (PNG) d(ii). Natural Gas Distribution System (PDF) [Link Updated 12 Nov 2010] e. Hurlburt Field As-built drawings [floor plans] (only available in Document Room) f. Stormwater Distribution System (PDF) [Link Updated 12 Nov 2010] |